beautypg.com

Slide gate installation (cont.) – Autoquip GATES SLIDING User Manual

Page 5

background image

4

____________________________________________________________


2.
Bolt the trolley channel header to the (3) gate posts with the hardware provided.


Filler

Panel

Gate

Trolley

Unistrut Track Mount



Gate Post

Gate Panel


3.
If not already attached, bolt the (2) trolleys to the top of the panel using the1/4” eye bolt and hex
nuts supplied. You will use three hex nuts on the eye bolt. One is installed on the eye bolt first, then the
eye bolt is installed through the trolley and panel. Then two nuts will be installed on the eye bolt, this
will allow you adjust the gate panel up and down to level the gate panel.

4. Slide the gate panel into the trolley channel, and slide the panel to the closed position. With the

gate panel in the closed position, you will need to install a TEK screw at the end of the unistrut to
prevent the panel from sliding out of the track. The Interlock Bracket on the gate panel will serve as
the gate stop when finished installing gate.

Guide Interlock Bracket

Guide

Handle

5. Locate and mark the center of the Gate panel. ( Note: The center of the gate is offset from the
carriage 3” to 5” for the guides, offset at the end post side.)

6. Locate and mark the center of the lift platform, and using a carpenters square mark a chalk line on

the floor to be used to center the gate with the lift. (See figure 2)

Slide Gate Installation (Cont.)