SHUT DOWN AND PARK

To shut down and park the machine, the procedures are as fol-
lows:

1.

Drive machine to a reasonably well protected area.

2.

Ensure boom is lowered over rear drive axle.

3.

Push in the Emergency Stop at Platform Controls.

4.

Push in the Emergency Stop at Ground Controls. Position
Platform/Ground Select switch to center OFF.

5.

If necessary, cover Platform Controls to protect instruction
placards, warning decals and operating controls from hostile
environment.

4.13

LIFTING AND TIE DOWN

Lifting

1.

Call JLG Industries or weigh the individual unit to find out
the Gross Vehicle Weight.

2.

Place the boom in the stowed position with the turntable
locked.

3.

Remove all loose items from the machine.

4.

Properly adjust the rigging to prevent damage to the
machine and so the machine remains level.