Sequencing cable adjustment, Sequencing cable adjustment -36 – JLG 41AM (3120752) Service Manual User Manual
Page 60

SECTION 2 - SERVICE PROCEDURES
2-36
– JLG Lift –
3120752
NOTE: Mast section-1 is fixed to the base and mast section-
2 is attached to the lift cylinder, these sections
require no adjustment.
3. Adjust one mast section at a time starting from the
back (section-3, section-4, etc.) of the mast and
work forward. (i.e.. if three is OK, then jump to four,
etc.)
4. To adjust, elevate the platform until the chain/cable
anchor adjust nuts are accessible at the front and
bottom of each mast section.
NEVER WORK UNDER AN ELEVATED PLATFORM UNTIL PLAT-
FORM HAS BEEN SAFELY RESTRAINED FROM ANY MOVEMENT
BY BLOCKING OR OVERHEAD SLING.
5. Start with the mast section which needs adjustment
and loosen the bottom (jam) nut on each chain/
cable.
6. Tighten (to raise mast section), or loosen (to lower
mast section) the adjusting nut against the anchor
plate on each chain/cable. Adjust the nut the
amount required to raise or lower the top of the mast
section to match the side profile shown in Figure 2-
7. when the mast is retracted. Be certain each chain/
cable pair is adjusted to equal tension. (The
threaded end of the chain/cable will need to be
restrained while tightening the adjust nut to keep the
chain/cable from twisting.)
7. Retract the mast all the way and check if the top of
the mast sections appear as shown in Figure 2-7.
8. Repeat steps (1) through (7) for remaining mast sec-
tions. ENSURE THAT ALL CHAIN/CABLE PAIRS
HAVE EQUAL TENSION.
9. Once mast section adjustment is completed, apply
loctite #242 to the threads under the (jam) nuts that
were loosened. Then re-tighten the loosened (jam)
nuts until tight against the top (adjust) nut. Chain/
cable should have slight tension but should not be
taut. Run mast through several cycles to verify
cable/chain adjustments and ensure no interference
exists between chain anchor brackets and mast.
Sequencing Cable Adjustment
1. Retract mast completely, and check each sequenc-
ing cable on outside of masts for excessive slack.
Adjust only to remove slack from cable.
2. Tighten nylock-nut just enough to remove excessive
slack from sequencing cable. The springs should
not be compressed more than 25% after adjusting.