beautypg.com

Hanging the tubes, Fig. 7 – L.B. White Sentinel Radiant Tube AT150 Center Mount User Manual

Page 11

background image

HANGING THE TUBES

Refer to Fig. 7 and the following instructions:

1. Slide a tube clamp over the non-swaged end of 10 ft.

aluminized tube. (One aluminized tube per kit.)

2. Install the tube over the swaged discharge tube on

the burner box.

a. Tube weld seam must be down.

b. Non-swaged end of tube must be completely

pushed over swaged end of adjoining tube.

c. Clamp must be centered over tube connection.

d. Clamp bolts must be up.

e. Clamp bolts must be tight.

-- Tighten both bolts firmly.
-- Tighten both bolts to 35 ft.-lbs.
-- Finish tightening bolts to 65 ft.-lbs.

3. Slide on hangers and connect to chains.

4. Connect and hang remaining tubes. F

Follow the

procedures given in Step 2.

5. T

The tube assembly should be either hung level, or
with a downward slope away from the burner box not
exceeding 1 in. for every 10 ft. of tube.

CLAMP

SWAGED TUBE

ON BOX

NON-SWAGED

TUBE END

HANGER

CLAMP

BOLTS UP

TUBE WELD

SEAM DOWN

BRIGHT

ALUMNIZED

TUBE

TUBE WELD SEAM

CLAMP

THIS

NOT THIS

POSITION CLAMP EVENLY

CLAMPS MUST BE

CENTERED OVER

SWAGED AND NON

SWAGED CONNECTIONS

FIG. 7

11