Air purging with vacuum pump, Air purging, Adding refrigerant – Amcor UCHW-H24AF2 User Manual

Page 22: Gas leakage inspection

background image

6

INSTALLATION & REPAIR GUIDE

Split Wall-Mounted air conditioner

*Air purging with vacuum pump

1.Check that pipelines connection have been properly

connected,remove the charging port cap,and connect

the manifold gauge and the vacuum pump to the

charging valve by service hoses as shown Fig.8.

2.Open the valve of the low pressure side of manifold

gauge,then,run the vacuum pump.Vacuum the indoor

unit and the connecting pipes until the pressure in

them lowers to below 1.5mmHG(The operation time

for vacuuming is about 10 minutes).When the desired

vacuum is reached,close the valve of the low pressure

of the manifold and stop the vacuum pump.

3.Disconnect the service hoses and fit the cap to

the charging valve.

4.Remove the blank caps,and fully open the spindles

of the 2-way and 3-ways valves with a service valve

wrench.

5.Tighten the blank caps of the 2-way and 3-ways

valves,applying the above torque Table 1.

*

Air purging

*

After the pipieline connection is done,use a leakage inspection device or soap suds to carefully check

if there is any leakage at the joints.This is an imporant step to ensure the quality of installation.Once

a leakage is detected,proper treatment should be taken immediately.

Lo

Hi

Indoor unit

Outdoor unit

Pressure gauge

Manifold gauge

Fig. 8

Vacuum pump

Union nut

Blank cap

Valve stem

Charging

port

Service hose

*Adding refrigerant

Refrigerant must be added if the piping measures more

than 5 metres(16'5") in length.This operation can only

be performed by a professional technician,for the

additional amount,see the table 3 below.

Additional refrigerant amount

Liquid pipe diameter 6.35(1/4")

(piping length-5)mx30g

or (piping length-16)ftx0.3oz

Liquid pipe diameter: 9.52(3/8")

(piping length-5)mx65g

or (piping length-16)ftx0.7oz

Table 3

*Gas leakage inspection

2-way valve

3-way valve