Howard Small Power User Manual
Page 16

Document 2.4.54 Revision 0
July 2006
Small Power Substation Transformers
16
Gaskets
Visually check all gaskets for cracking or other signs of
deterioration. Replace as necessary. When replacing
a gasket carefully clean mating surfaces to remove
any rust, dirt, transformer fluid, old gasket material, or
other contamination that might prevent a good seal.
Use an appropriate gasket cement when installing new
gaskets. Do not reuse old gaskets. Six months after
replacing a gasket, check and retighten if necessary.
Additional Maintenance Instructions
Contact the Howard Substation Transformer Division for
additional maintenance instructions.
Repair Parts
Repair parts can be ordered from the Howard
Substation Transformer Division. A description of the
part and the transformer serial number will be required
to ensure that the correct part has been ordered.
Warranty Claims
The Howard Substation Transformer Division should
be notified immediately when problems are discovered
during the warranty period. All warranty repairs must
be made or approved by the Howard Substation
Transformer Division.