gaskets
visually check all gaskets for cracking or other signs of
deterioration. Replace as necessary. When replacing
a gasket carefully clean mating surfaces to remove any
rust, dirt, transformer fluid, old gasket material, or other
contamination that might prevent a good seal. Use an
appropriate gasket cement when installing new gaskets.
Do not reuse old gaskets. Six months after replacing a
gasket, check and retighten if necessary.
Additional Maintenance Instructions
Contact the Howard Substation Transformer Division for
additional maintenance instructions.
Repair Parts
Repair parts can be ordered from the Howard Substation
Transformer Division. A description of the part and the
transformer serial number will be required to ensure that
the correct part has been ordered.
Warranty Claims
The Howard Substation Transformer Division should
be notified immediately when problems are discovered
during the warranty period. All warranty repairs must be
made or approved by the Howard Substation Transformer
Division.