Perform the following to close the regulator, A. close the source valve, C. rotate the wheel fully counterclockwise – APTech SL 5800 User Manual
Page 4: A. open a downstream valve to initiate flow
Operation Manual
Pressure Regulators
Manual 15000006 Rev 6
Page 4 of 4
c.
In order to obtain a specific set point under flowing conditions, continue to rotate the
wheel counterclockwise to reduce the delivery pressure below the desired set point. Then,
rotate the wheel clockwise to increase the delivery pressure to obtain the set point at the
desired flow condition.
3. Perform the following to close the regulator.
a.
Close the source valve.
b.
Vent to atmospheric pressure on both sides of the pressure regulator.
c.
Rotate the wheel fully counterclockwise.
F. Pneumatically Actuated Regulator Operation (PA models)
Note: A pressure regulator should not be used as a positive shut-off device.
Caution: Do not vent or otherwise reduce the actuation control pressure under non-flowing
conditions as damage to the regulator internal parts or leakage may result.
Caution: Do not pressurize the regulator outlet except by slowly increasing the actuation control
pressure as damage to the regulator internal parts or leakage may result.
1. Perform the following to open the regulator or increase the regulator delivery pressure set
point.
a.
Before opening the source valve, verify that the actuation control pressure is at
atmospheric pressure.
b.
Slowly open the source valve to pressurize the regulator high pressure port.
c.
Slowly increase the actuation control pressure to increase the delivery pressure to the
desired set point.
Note: The delivery pressure will decrease as the flow rate is increased. In order to obtain
a specific delivery pressure at flow, adjust the regulator to the desired delivery pressure
while operating at the desired flow conditions. Be aware the delivery pressure will rise
when the flow is shut-off or decreased downstream.
2. Perform the following to decrease the regulator delivery pressure set point.
a.
Open a downstream valve to initiate flow.
b.
Slowly reduce the actuation control pressure to reduce the delivery pressure.
c.
In order to obtain a specific set point under flowing conditions, continue to decrease the
actuation control pressure to reduce the delivery pressure below the desired set point.
Then, increase the actuation control pressure to increase the delivery pressure and obtain
the set point at the desired flow condition.
3. Perform the following to close the regulator.
a.
Close the source valve.
b.
Vent to atmospheric pressure on both sides of the pressure regulator.
c.
Vent or otherwise reduce the actuation control pressure to atmospheric pressure.
Please contact the factory or your local representative to answer questions or for further
information.
- SL 5500 SL 5400 SL 5200 AK 9200 AZ 9200 AP 9200 AK 91PA AZ 91PA AP 91PA AK 90PA AZ 90PA AP 90PA AK 9000 AZ 9000 AP 9000 AK 2700 AZ 2700 AP 2700 AK 1900 AZ 1900 AP 1900 AK 1700 AZ 1700 AP 1700 AK 1600 AZ 1600 AP 1600 AK 15PA AZ 15PA AP 15PA AK 1500 AZ 1500 AP 1500 AK 14PAT AZ 14PAT AP 14PAT AK 1400T AZ 1400T AP 1400T AK 1300 AZ 1300 AP 1300 AK 12PA AZ 12PA AP 12PA AK 1200 AZ 1200 AP 1200 AK 1100 AZ 1100 AP 1100 AK 1000T 10PA AZ 1000T 10PA AP 1000T 10PA AK 1000 AZ 1000 AP 1000 AK 500 AZ 500 AP 500