6 uncrating your new chiller ! warning – Sterlco S Series Central Chilling Stations User Manual
Page 17

SSC Series Central Chilling Stations
Page 17 of 86
2-6 Uncrating Your New Chiller
! WARNING !
DUE TO THE SIZE AND WEIGHT OF SSC SERIES CHILLERS,
STERLING RECOMMENDS USING BONDED PROFESSIONAL
MILLWRIGHTS TO UNLOAD AND MOVE SSC SERIES
CHILLERS.
Rig the chiller from the frame only, using spreader bars to prevent
load transfer to any chiller components. Rig the frame from at least
four points and balance the load before lifting to clear the skid. Use
a forklift of adequate size when lifting the chiller by the fork
pockets.
Insert the forks all the way into the pockets and be sure to balance
the load before lifting the chiller to clear the skid. Lift only as high
as necessary. Use a pry bar to free the skid if necessary. Lower
slowly. Retain the crating in case reshipment is necessary due to
hidden shipping damage.
Caution!
Due to the weight of these units, use extreme caution
when moving and placing SSC Series chillers.
.