beautypg.com

Hot cold open – Pfister 8E8-CT1C User Manual

Page 5

background image

5

8 VALVE FUNCTION (Fig.D)

By lifting the Lever Handle (1) up, the valve will be activated

allowing water to flow. The water flow will increase by

continuing to lift up the Lever Handle (1). By rotating the

Lever Handle counter-clockwise, the water temperature will

decrease to cold flow only. By rotating the Lever Handle

clockwise, the water temperature will increased to hot flow

only.
9 FLUSHING (Fig.E)

After installation is complete, turn water supply valves on

and turn faucet on. Allow both hot and cold water to run at

least one minute each until all foreign matter has cleared

the line. While water is running, check for leaks.
10 CLEANING THE AERATOR (Fig.F)

It is advisable to periodically clean the aerator, in order

to avoid build-up of dirt and limestone, which in time

could gradually limit the water flow. To clean the Aerator,

disassemble Aerator Housing by separating the Aerator

Head (5), Basket (6) and Washer (7). Once parts have been

cleaned, reassemble by reversing steps.
11 WALL HOOK INSTALLATION (Fig.G)

Drill one

1

/

4

” Dia. Hole (1). If installing into a stud, drill a one

1

/

8

” Dia. hole and do not use the anchor (2). Insert anchor

(2) into hole (1) and tap flush with wall. Place wall mount

(3) onto wall and insert mounting screw (4) through wall

mount hole (1) and tighten until wall mount (3) is flush with

the wall. (Do Not Over Tighten!) Insert front cover (5) into

Wall Mount (3). Shower hose (6) hangs on wall mount hook

(7) as shown.

E

5

6

7

F

1

4

2

3

3

7

7

6

6

5

G

D

D

HOT

COLD

OPEN

This manual is related to the following products: