Appendix a - forms – ATS CyberChiller Series User Manual
Page 35

(©October, 2006)
CyberChiller Series Installation, Operation & Maintenance Manual
APPENDIX A - FORMS
Stulz Air Technology Systems Inc.
Frederick, Maryland USA 21704
Telephone: (301) 620-2033 Facsimile: (301) 620-1396
Checklist for Completed Installation
Frederick, Maryland USA 21704
CyberChiller Series
Telephone: (301) 620-2033
Facsimile: (301) 620-1396
❏
1
Proper clearances for service access have
been maintained around equipment.
❏
2
Equipment is level and mounting fasteners (if
applicable) are tight.
❏
3
Piping completed to refrigerant or coolant loop
(if required).
❏
4
All field installed piping leak tested.
❏
5
Refrigerant charge added (if required).
❏
6
Incoming line voltage matches equipment
nominal nameplated rating ± tolerances.
❏
7
Main power wiring connections to the
equipment, including earth ground, have been
properly installed.
❏
8
Customer supplied main power circuit breaker
(HACR type) or fuses have proper ratings for
equipment installed.
❏
9
All wiring connections are tight.
❏
10
Control wiring connections completed to
evaporator and condenser/condensing unit
(if required), including wiring to wall mounted
control panel and optional controls.
❏
11
Foreign materials have been removed from
inside and around all equipment installed
(shipping materials, construction materials,
tools, etc.).
❏
12
Compressors and pumps rotate freely without
unusual noise.
❏
13
Inspect all piping connections for leaks during
initial operation.
A-1