9. PUMP INSTALLATION

9.1 Positioning

The pump should be installed flat on a rigid base by

means of the four Ø .6” feet. The base should

be rigid enough to avoid any misalignment or flexing of the

pump/transmission coupling axis due to the torque

involved during operation.

9.4 Suction (continued)

Plunger pumps are not self priming therefore a positive

suction head should always be provided. Information for

the correct suction line:

1. Internal diameter should be at least 1-1/2”, in any

point, possibly larger depending on the drop in

pressure due to the length and shape of the line.

2. Should be as straight as possible minimizing changes

in size and direction and positioned in such a way

to allow air pockets and bubbles to escape.

3. Should be perfectly airtight.
4. Should be completely free from 90o elbows, diameter

reductions, counter slopes, “T” connections and

should not be connected to other pipelines.

5. Should be positioned in such a way to prevent the pipe

emptying after the pump stops.6.

Do not use high

pressure flexible hoses for the suction line.

7. Do not use high pressure hydraulic fittings like 90o

elbows, high pressure adapters, high pressure 3 or

4 way nipples and so on.

8. Do not install any kind of detergent injector along the

suction line.

9. Do not install standing valves, check valves or other

kind of one-way valves.

10. Make sure that the feed tank capacity and the water

minimum level do not give rise to turbulence at the

tank outlet port, which, in turn, might create

cavitation at the pump.

11. Do not connect the by-pass line from the valve directly

to the pump suction line.

12. The water flow from the valve should be directed back

in the tank. Make sure that the by-pass and tank

feeding flows to not give rise to turbulence at the

tank outlet port, which, in turn, might create

cavitation at the pump. Proper baffle plates should

be provided inside the tank.

13. Before connecting the suction line to the pump inlet

port make sure the pipe is perfectly clean inside.

9.2 Direction of rotation

Fig. 5 shows the correct direction of rotation looking at the

pump from the fluid end side. Two arrows stamped on the

crankcase nearby the crankshaft provide the information

as well.

9.3 Water connections

In order to isolate the high pressure equipment from the

pump vibrations it is suggested, where applicable, to use

flexible hoses for both suction and delivery lines at least

for the first length.

9.4 Suction Line

VS pumps require an inlet pressure at the suction port

of at least 44 PSI up to 73 PSI. The feeding pump should

be of a centrifugal type , supply at least twice the rated VS

pump flow rate at the above required pressures in any

working condition at any pump speed. The feed pump

should be operated independently from the plunger pump.

The VS pump should be started only when the inlet

pressure is at least 44 PSI. A pressure switch to control the

correct inlet pressure should always be installed in the

suction line after the filters.