background image

50629

2

3/04 Issue #2

D. Installation:

The Omnicell is fully assembled when shipped and ready for installation.
With the vessel, tank, or hopper supported safely on blocks, jacks or by
other means:

• Set each OMC assembly base onto a flat surface centered under

the support leg/support flange

• Loosely bolt the flange of the support legs to the OMCs' load

mounting plates

• Select the checking that best suits the application and rotate the

posts and/or mounting yokes for proper checking clearances
(there are many settings variations that can be used to get the
right checking clearances).

• Ensure the vessels load 'legs' are directly over the center of the

load cell's load mounting plate

• Mark the holes where the anchor bolts will be placed, or drill

down through the holes in the base

• Drill and set anchor bolts, then mount the base and secure, with

lock washers and nuts

• Wire the load cell into the junction box or sectional controller

or QMB using the color code listed above, or printed on the cable.

• Use the calibration sheet packed with each cell for Intalogix™

Technology instruments' exact settings of cell outputs.

• Carefully lower the vessel onto the cells ensuring that any one or

more cells are not overloaded during the process

• Use the proper manual for instrument calibration

1

0

1