Consistent gas pressure is essential at ALL gas connections. It is recommended that a 3/4-inch pipe gas loop

be installed in the supply line serving a bank of dryers. An in-line pressure regulator must be installed in the

gas supply line (header) if the (natural) gas pressure exceeds 12.0 inches of water column (W.C.) pressure.

NOTE: A water column

(W.C.)

test pressure of 3.5 - 4.0-inches for natural gas and 11.0-inches for

L.P. (liquid propane) dryers is required at the gas valve pressure tap of each dryer for proper
and safe operation.

A 1/8" N.P.T. plugged tap, accessible for a test gauge connection, must be installed in the main gas supply

line immediately upstream of each dryer.

IMPORTANT: Pipe joint compounds that resist the action of natural gas and L.P. gas must be used.

IMPORTANT: Test ALL connections for leaks by brushing on a soapy water solution (liquid

detergent works well).

WARNING: NEVER TEST FOR LEAKS WITH A FLAME!!!

ALL components/materials must conform to National Gas Code specifications. It is important that gas

pressure regulators meet applicable pressure requirements and that gas meters be rated for the total amount

of ALL the appliance BTU's being supplied.

IMPORTANT: The dryer and its individual shut-off valve must be disconnected from the gas supply

piping system during any pressure testing of that system at test pressures in excess of

1/2 psig (3.5 kPa).

NOTE: The dryer must be isolated from the gas supply piping system by closing its individual manual

shut-off valve during any pressure test of the gas supply system at test pressures equal to or

less than 1/2 psig (3.5 kPa).