beautypg.com

Installation – Poweramp CentraAir AIR POWERED User Manual

Page 15

background image

13

4111-0034 — July. 2012
Aug. 2012

INSTALLATION

A— Front of Dock Pit
B— Dock Leveler Frame

C— Side Pit Curb Angle
D— Gap [3/4 in. (19 mm)

Minimum]

E— Pry Locations
F— Rear Hinge Frame

Angle

G— Rear Pit Curb Angle
H— Flare Bevel Weld, Typical

(To Fit Spacing)

8.

With rear hinge frame angle (F) tight against rear
pit curb angle (G), perform/check the following:

Pry between the platform and rear hinge frame
angle at locations (E) to make sure rear edge of
platform is parallel to the rear hinge frame angle
(F).

Gap (D) must exist equally along both sides of
leveler so weather seal (if equipped) will not
bind during dock leveler operation.

9.

If gap (D) cannot be obtained equally at both sides
of leveler, grind or add material at the rear edge of
rear hinge frame angle (F) as needed.

10. Allow the dock leveler to rest fully on the shim

stacks. Check that a smooth and level transition
exists between the dock floor and the dock leveler
platform. Add or remove shims as necessary until
a smooth transition is obtained.

11. If leveler cannot be squared and/or made level as

instructed in steps 8 — 10, contact Poweramp

®

Technical Services.

G

H

E

C

F

C

D

D

6 in.

(152 mm)

3/8 in.

(9.5 mm)

A

B