Estimated timeline, Total customer 1 hr, Total distributor/technician 15 hrs – Hydra-Flex Aqua-Lab MD Installation Manual User Manual

Page 7: Total electrician 4 hrs, Total plumber 4 hrs

background image

Installation Manual

© Hydra-Flex Inc 2011

- 5 -

Estimated Timeline

Pre-Installation

Who

Task

Est. Time

Distributor & Customer

Determine location to install equipment

1 hr

Plumber

Install water supply line

4 hrs

Electrician

Install electrical supply line

4 hrs

Technician

Label all controller relays at MCC or junction box

1 hrs

Technician

Run solution and air lines

5 hrs

Technician

Install air supply line

1 hr

Total Labor Hours 16 hrs


Installation

Who

Task

Est. Time

Technician

Hang equipment

1 hr

Technician

Connect water, air and solution lines

1 hr

Technician

Connect control leads to main controller or junction box

2 hr

Distributor / Technician

Startup (injector, metering tip and nozzle selection)

3 hr

Distributor / Technician

Document configuration

1 hr

Total Labor Hours 8 hrs


Post Installation

Who

Task

Est. Time

Distributor

Monitor & record performance

2 hrs / wk

Distributor

Maintenance per schedule or as needed

Total Customer

1 hr

Total Distributor/Technician

15 hrs

Total Electrician

4 hrs

Total Plumber

4 hrs

Installation takes approximately two days for a two technician team. An electrician and a plumber are needed for
half a day on the first day.