Lifting and handling the unit, Warning – AAON SA-070 User Manual
Page 19

19
Consult your local building codes for
additional service clearance requirements.
Allow adequate space for piping access and
panel removal. Condenser water piping and
condensate drain connections are near the
bottom on the back of the unit.
Figure 1 - SA Series Unit with Right Intake
Lifting and Handling the Unit
Before lifting unit, be sure that all shipping
material has been removed from unit.
If cables or chains are used to hoist the unit
care should be taken to prevent damage to
the cabinet.
Secure hooks and cables at the all lift points
provided near the fan section at the top of
the unit.
UNIT HANDLING
Incorrect lifting can cause damage to
the unit, injury or death. Lifting
equipment capacity should exceed
unit weight by an adequate safety
factor. Always test lift unit not more
than 24 inches high to verify proper
center of gravity lift point.
WARNING