Installation
5 Installation
5.1
Preparing for installation
Check the following points:
•
Machine freely accessible from all sides
•
Do not close ventilation grids and holes
•
Suffi cient room for installing and removing pipes
and for maintenance work, particularly for install-
ing and dismantling the machine
•
No external vibration effect
•
Do not suck any hot exhaust air from other ma-
chines into the cooling system.
To remove the outlet grid (Fig. 2/G), the inlet grating (Fig. 2/G
1
) and the housing lid (
Fig. 3/b
) at
least 30 cm of space must be available for maintenance work.
You must also ensure that the
cooling air inlets (Fig. 2/E) and cooling air outlets (Fig. 2/F) must be at least 10 cm away from the
nearest wall (outgoing cooling air must not be sucked in again).
5.2
Installation
NOTICE
The machine may only be operated when it is
set up horizontally.
Material damage resulting from the machine
tipping over and falling.
When installed at more than 1000 m above sea
level a reduction in power is noticeable. In this
case we would ask you to contact us.
Ensure that the foundation complies with the follow-
ing conditions:
•
Level and straight
•
The bearing surface must be able to bear the
weight of the machine
It must be possible to install the machine on a fi rm foundation without anchoring. When installing
on a substructure we recommend fi xing with fl exible buffers.