reading on the discharge pressure gauge or by a
quieter operation. The pump may not prime imme­
diately because the suction line must first fill with
liquid. If the pump fails to prime within five minutes,
stop it and check the suction line for leaks.

After the pump has been primed, partially close the
discharge line throttling valve in order to fill the line
slowly and guard against excessive shock pres­
sure which could damage pipe ends, gaskets,
sprinkler heads, and any other fixtures connected
to the line. When the discharge line is completely
filled, adjust the throttling valve to the required flow
rate.

Do not operate the pump against a
closed discharge throttling valve for
long periods of time. If operated against
a closed discharge throttling valve,
pump components will deteriorate, and
the liquid could come to a boil, build
pressure, and cause the pump casing to
rupture or explode.

Leakage

No leakage should be visible at pump mating sur­
faces, or at pump connections or fittings. Keep all
line connections and fittings tight to maintain maxi­
mum pump efficiency.

Liquid Temperature And Overheating

The maximum liquid temperature for this pump is
160

_F (71_C). Do not apply it at a higher operating

temperature.

Overheating can occur if operated with the valves
in the suction or discharge lines closed. Operating
against closed valves could bring the liquid to a
boil, build pressure, and cause the pump to rup­
ture or explode. If overheating occurs, stop the
pump and allow it to cool before servicing it. Refill
the pump casing with cool liquid.

Do not remove plates, covers, gauges,
pipe plugs, or fittings from an over­
heated pump. Vapor pressure within
the pump can cause parts being disen­
gaged to be ejected with great force. Al­
low the pump to completely cool before
servicing.

As a safeguard against rupture or explosion due to
heat, this pump is equipped with a pressure relief
valve which will open if vapor pressure within the
pump casing reaches a critical point. If overheating
does occur, stop the pump immediately and allow
it to cool before servicing it. Approach any over­
heated pump cautiously
. It is recommended that
the pressure relief valve assembly be replaced at
each overhaul, or any time the pump casing over­
heats and activates the valve. Never replace this
valve with a substitute which has not been speci­
fied or provided by the Gorman‐Rupp Company.

Strainer Check

If a suction strainer has been shipped with the
pump or installed by the user, check the strainer
regularly, and clean it as necessary. The strainer
should also be checked if pump flow rate begins to
drop. If a vacuum suction gauge has been in­
stalled, monitor and record the readings regularly
to detect strainer blockage.

Never introduce air or steam pressure into the
pump casing or piping to remove a blockage. This
could result in personal injury or damage to the
equipment. If backflushing is absolutely neces­
sary, liquid pressure must be limited to 50% of the
maximum permissible operating pressure shown
on the pump performance curve.

Pump Vacuum Check

With the pump inoperative, install a vacuum gauge
in the system, using pipe dope on the threads.
Block the suction line and start the pump. At oper­
ating speed the pump should pull a vacuum of 20
inches (508 mm) or more of mercury. If it does not,
check for air leaks in the seal, gasket, or discharge
valve.