PNEG-1375 Farm/Commercial Distributor Cable Control

5. INSTALLATION

Calibrating the Distributor Spout and the Lower Cable Control Wheel

1. Place the discharge spout index trigger to the far right as shown in

Figure 5O

.

2. Using the Index Number Decal (Decal part number DC-1799), peel off one of the numbers

(numbered 1 through 10) and place on the Spout Decal Plate in front of the Spout Position
Arrow

(See Figure 5N on Page 21)

.

3. Move to the next spout by pulling up on the Control Handle to disengage the Index Trigger

while rotating the Lower Cable Control Wheel counter-clockwise.

4. Repeat

Step 2

& 3

until all spouts have been labeled on the Spout Decal Plate.