5. Operation Procedures
22
PNEG-1079 6", 8" and 10" Vertical Bin Unload Auger
Capacity
The results or capacities of screw conveyors or augers can vary greatly under diverse conditions. Different
materials, moisture content, amounts of foreign matter, angle of operation, methods of feeding and speed
all play a role in performance of the auger. Capacities listing in the
will be achieved when
augering reasonably dry grain. Maximum possible capacity will be less with high moisture grain (above
15%) than with dry grain.
Clean-Up
1. Check to see that all guards listed in the assembly instructions are in place and secured
and functional.
2. Check all safety decals and replaced any that are worn, missing or illegible. The safety decals are
. Safety decals may be obtained free of charge from the dealer or ordered
from the factory.
3. Check to see that all fasteners are securely in place.
Storage Preparation
1. Close all wells to discharge tube.
2. Be sure the unload tube is empty.
3. Make sure power source is disconnected and locked out.
4. Check to see that all fasteners are secure.
Lubrication and Maintenance
The flange bearing on the head and tail ends of the auger should be lubricated at frequent intervals.
Check belt tension on motor drive belts for electric drive units.
Lubricate and check drive chain at frequent intervals. Adjust chain tension, if necessary.
Check to make sure all guards are in place.
Unit
Capacity BPH
6"
850-1250
8"
2000-2500
10"
3250-3750
Never clean, adjust or lubricate a machine that is in operation.