Treated Wood Base Foundation

1. The wood base will be assembled out of 4 x 6

and 2 x 12 treated lumber, hardware (including

galvanized lag bolts/deck screws), and

fill material, such as gravel (none provided).

2. Assemble the 2 x 12 pieces in the dimensions

shown in the diagram below. The wood will

need to be trimmed to fit. Make certain that the

assembly is square and level. The diagonal

dimensions, from outside corner to outside corner,

should be 123

3

/

4

″ each. Also use a level to

ensure that the base is even. If needed, fill under

sections of the base to make sure it is level.

Figure C: Wood Base Dimensions

3. Assemble the 4 x 6 pieces on top of the

base you just assembled, as shown in the

cross section below. Fill the base with the

fill material up to the top of the 4 x 6's.

4. There are

four Floor Plates to position on

the foundation; the Front Floor Plate (17),

the Rear Floor Plate (16),

and two Side Floor Plates (34).

(See Figure G on page 8.)

5. Match the length of each of the

four Floor Plates (16, 17, 34) with the appropriate

length of each edge of the base.

Place the Front Floor Plate (17) on

the side that the door will face.

NOTE: Position the four Floor Plates (16, 17, 34)

with their outer edges overhanging the outer edges

of the base, as shown below.

Do not secure

the Floor Plates to the Base at this time.