Vertical Vent Installation

Once the vent terminal location has been

determined, make a hole through the roof

and interior ceiling to accommodate the

vent pipe.
Complete the vent pipe installation to the

water heater's vent connector fitting on the

blower outlet.
Support vertical or horizontal lengths as

previously mentioned.
Install adequate flashing where the vent

pipe passes through the roof.

Determine the vent terminal height and cut

vent pipe accordingly. Refer to the above

section for proper vent terminal height.
Connect vent elbow onto vertical pipe

through roof.
Connect short piece of vent pipe

(approximately 3" long) to elbow, then

insert 1/2" mesh metal screen into terminal

elbow and join it to the short piece of vent

pipe.

Vertical Vent Termination Location

The location of the vent terminal depends on the following

minimum clearances and considerations (see illustration):

Minimum twelve (12) inches above roof.
Minimum twelve (12) inches above anticipated snow level.
Maximum twenty-four (24) inches above roof level without

additional support for vent.

Four (4) feet from any gable, dormer or other roof structure

with building interior access (i.e., vent, window, etc.).

Ten (10) feet from any forced air inlet to the building. Any

fresh or make-up air inlet such as a dryer or furnace area is

considered to be a forced air inlet.

Short Piece of Vent Pipe

Min. 12" Above Roof

Min. 12" Above

Anticipated Snow

Level.

Max. 24" Above Roof

(Without Additional

Support)

Insert 1/2" Mesh Protective

Screen Inside Terminal Elbow

Vent Pipe

Through Roof

Elbow

Horizontal Vent Installation

Once the vent terminal location has been determined, make a

hole through the exterior wall to accommodate the vent pipe.

Vent pipe must exit exterior wall horizontally only.
Insert a small length of vent pipe through the wall and connect

the coupling as shown to the left.
Place the 1/2" mesh metal screen inside the terminal fitting

and connect it as shown to the vent pipe on the exterior of the

building.
Complete the rest of the vent pipe installation to the water

heater's vent connector fitting on the blower outlet.
If necessary support horizontal run as previously mentioned.

*

FOR THE 60 GALLON MODELS ONLY a 90° vent

termination must be used and must be at least 2" from the wall.

2' x 2' Sheet

Metal Shieldon

Brick or Masonry

Walls

Outside of

Building Wall

From

Water Heater

Vent Pipe

Pipe Coupling

*

Vent Terminal

with

1

/

2

" Mesh

Protective

Screen Inside

Vent Terminal