Job aid: cable stripping requirements, Removing the power filler panel – Nortel Networks NN46200-310 User Manual
Page 30

30
DC power supply installation
1
Strip 0.81 in. (2.1 cm) of insulation from the ends of the cables.
2
Crimp the lugs onto the cables using a standard crimping tool.
CAUTION
Risk of injury by electric shock
Failure to properly crimp the lugs onto the cables
constitutes a safety hazard.
3
If necessary, use a heat gun to shrink the tubing around the
cable.
--End--
Job aid: Cable stripping requirements
The illustrations in this section provide details about cable stripping
requirements for the 8005DI DC and 8005DC power supplies.
Removing the power filler panel
A power filler panel maintains the proper cooling airflow in the Ethernet
Routing Switch 8300 chassis. You must remove the power filler panel from
the power bay when you install a power supply in a bay for the first time.
Nortel Ethernet Routing Switch 8300
Installation — DC Power Supply
NN46200-310
01.01
Standard
9 June 2008
Copyright © 2008 Nortel Networks
.