beautypg.com

Final installation checklist – Samsung DV219AGW User Manual

Page 17

background image

installing your dryer

_17

6. With a level, check your Dryer and make necessary adjustments to the leveling legs.
7. At this time, make sure all gas connections (on gas models), exhaust and electrical connections are

complete. Plug in your Dryer, and check operation by using the checklist below.

8. (GAS MODELS ONLY : DV219AGW)

The burner may not ignite initially due to air in the gas line. Allowing your Dryer to operate on a heat
setting will purge the line. If the gas does not ignite within 5 minutes, turn your Dryer off and wait 5
minutes. Be sure the gas supply to your Dryer has been turned on. In order to confirm gas ignition,
check the exhaust for heat.

FINAL INSTALLATION CHECKLIST

Dryer is plugged into electrical outlet and is properly grounded.

Exhaust ductwork is hooked up and joints are taped.

Plastic flexible duct is NOT used.

Used rigid or stiff-walled flexible metal vent material.

Dryer is leveled and is sitting firmly on the floor.

Gas models – gas is turned on with no gas leaks.

Start your dryer to confirm that it runs, heats, and shuts off.

01 installing your dryer

DV219AGW-02691A_EN.indd 17

2009-01-30 ¿АИД 6:19:25

This manual is related to the following products: