49 INITIAL LIGHTING - continued

1. Hand the User's Instructions to the Householder and

explain his or her responsibilities under the current Gas
Safety (Installation and Use) Regulations or rules in force.

2. Draw attention to the Lighting Instruction label affixed to the

controls pod door.

3. Explain and demonstrate the lighting and shutting down

procedures.

4. The operation of the boiler and the use and adjustment of

ALL system controls should be fully explained to the
Householder, to ensure the greatest possible fuel
economy, consistent with household requirements of both
heating and hot water consumption.
Advise the User of the precautions necessary to prevent
damage to the system and to the building, in the event of
the system remaining inoperative during frosty conditions.

5. Explain the function and the use of the boiler thermostat

and external controls.

6. Explain the function of the boiler overheat thermostat

and emphasise that if cutout persists, the boiler should
be turned off and a registered CORGI installer
consulted. In IE contact a Competent Person.

7. Explain and demonstrate the function of time and

temperature controls, radiator valves etc., for the
economic use of the system.

8. If any programmer is fitted draw attention to the

Programmer User's Instructions and hand them to the
Householder.

9. After installation and commissioning please complete the

Commissioning Checklist before handover to

the customer. For IE, it is necessary to complete a
"Declaration of Conformity" to indicate compliance to I.S.
813:2002.

10. Stress the importance of regular servicing by a CORGI

registered installer and that a comprehensive service
should be carried out AT LEAST ONCE A YEAR. In IE
servicing work must be carried out by a Competent Person.

After completing the installation and commissioning of the
system the installer should hand over to the householder by
the following actions
:

51 HANDING OVER

50 GENERAL CHECKS

Make the following checks for correct operation:
1.
Set the boiler thermostat knob to position 6 and operate the mains

on/off switch. Check that the main burner lights and extinguishes
in response.

2. The correct operation of ANY programmer and all other system

controls should be proved.
Operate each control separately and check that the main burner or
circulating pump, as the case may be, responds.

3. Check that the casing is sealed correctly and compressing the

sealing strip all around the casing.

4. Water Circulating System

a. With the system HOT, examine all water connections for

soundness.

b. With the system still hot, turn off the gas, water and electricity

supplies to the boiler and drain down, in order to complete the
flushing process.

c. Refill and vent the system, clear all air locks and again check for

water soundness.

d. Balance the system.

WARNING.

The boiler MUST NOT be operated with the casing
removed.

cla7679

cla7678

controls support

fixing screws

19. Swing the control box back into

its working position and secure.

20. Refit the controls pod to the

boiler casing and tighten the 2
front fixing screws.

21. Close the pod door.

Knob Setting

Flow Temperature

o

C

o

F

1

54

130

2

60

140

3

66

150

4

71

160

5

77

170

6

82

180

5. Finally, set the controls to the user's requirements.