beautypg.com

English, Vi. electrical supply, V. final assembly – Middleby Marshall PS570S User Manual

Page 11: Vii. gas supply caution

background image

11

ENGLISH

Figure 2-12 - Crumb trays

Crumb trays

with slots

Lower oven

cavity ONLY

All upper oven

cavities

Crumb trays

without slots

Figure 2-13 - Utility Connection Locations

Electrical

Junction Box

One per oven

cavity

VI. ELECTRICAL SUPPLY

WARNING

Authorized supplier personnel normally accomplish

the connections for the ventilation system, electric supply,

and gas supply, as arranged by the customer. Following

these connections, the factory-authorized installer can

perform the initial startup of the oven.

NOTE: The electric supply installation must satisfy the

requirements of the appropriate statutory authority, such as the

National Electrical Code (NEC), ANSI/NFPA70, (U.S.A.); the

Canadian Electrical Code, CSA C22.2; the Australian Code

AG601; or other applicable regulations.

NOTE: The electric supply connection must meet all national

and local electrical code requirements.

Check the oven serial plate before making any electric supply

connections. Electric supply connections must agree with data

on the oven serial plate.

A fused disconnect switch or a main circuit breaker (customer

furnished) MUST be installed in the electric supply line for each

oven cavity. It is recommended that this switch/circuit breaker

have lockout/tagout capability.

The supply conductors must be of the size and material (cop-

per) recommended. Refer to the wiring diagram inside the

machinery compartment of the oven. Electrical specifications

are also listed on the oven's serial plate.

The oven requires a ground connection to the oven ground

screw located in the electrical junction box. (The box is shown

in Figure 2-13.) If necessary, have the electrician supply the

ground wire. Do NOT use the wiring conduit or other piping for

ground connections!

Gas Inlet

One per Single,

Double, Triple,

or Quad Oven

V. FINAL ASSEMBLY

1. Refer to Figure 2-12 to determine the correct locations of

the crumb trays.

2. Install the crumb trays underneath the conveyor as shown

in Figure 2-12. First, place the inside edge of the tray onto

the retainer. Then, swing the outside edge of the tray up and

into place.

3. Press the conveyor end stop and rear stop down over the

edge of the conveyor frame.

All electric supply connections are made via the electrical

junction box on the rear of the oven, shown in Figure 2-13. The

power lines then connect to the oven circuits through safety

switches located inside the machinery compartment and each

blower motor compartment. These switches interrupt electric

power to the oven when the Machinery Compartment Access

Panel is opened, OR when either of the rear shrouds is

removed.

Refer to the wiring diagram inside the machinery compartment

of the oven to determine the correct connections for the electrical

supply lines. Connect the supply as indicated on the wiring

diagram. Be sure to connect the electrical supply ground wire

to the oven ground screw located in the junction box on the rear

of the oven.

VII. GAS SUPPLY

CAUTION

DURING PRESSURE TESTING NOTE ONE OF THE FOLLOWING:
1. The oven and its individual shutoff valve must be discon-

nected from the gas supply piping system during any

pressure testing of that system at test pressure in excess

of 1/2 psi (3.45 kPa).
2. The oven must be isolated from the gas supply piping

system by closing its individual manual shutoff valve dur-

ing any pressure testing of the gas supply piping system at

test pressure equal to or less than 1/2 psi (3.45 kPa).

3. If incoming pressure is over 14” W.C. (35mbar), a sepa-

rate regulator MUST be installed in the line BEFORE the

individual shutoff valve for the oven.
WARNING:
To prevent damage to the control valve regula-

tor during initial turn- on of gas, it is very important to open

the manual shutoff valve very slowly.
After the initial gas turn-on, the manual shutoff valve must

remain open except during pressure testing as outlined in

the above steps or when necessary during service main-

tenance.

SECTION 2 - INSTALLATION