INSTALLATION MANUAL FOR INDOOR UNIT

Material of connection pipe and thermal insulation

Foam polyethylene pipe, thickness over 10mm

Stiff PVC pipe VP 20mm (inside diameter)

Material of connection pipe

Material of thermal insulation

Warning

!

Perform with two spanners

Depenbing on the outdoor unit.For details,please refer to the operation manual
attached with outdoor unit.

The permitted length and fall of connection pipe

When performing the connection work of flare nut,
connect all the refrigerant pipe.
When connecting the connection pipe of indoor
unit, must use two spanners to perform.
For the installation torque, please refer the
following Table.

Connection of refrigerant pipe

During installation, if refrigerant leakage occurs, please immediately take
ventilation measure. If the refrigerant gas meet the fire, it may generate poisonous
gas.
After finishing installation work, please make sure there is no refrigerant leakage.
If the leaked refrigerant gas meet heater and oven, etc. fire sources, it may
generate poisonous

.

Material of
connection pipe

Gas side
Liquid side

Dimension of
connection pipe

12.7

6.35

Phosphorus oxidized copper seamless pipe
(TP2) for air conditioner

External diameter of
connection pipe (mm)

Installation torque (N.m) Add to installation torque (N.m)

6.35

11.8(1.2kgf.m)

13.7(1.4kgf.m)

12.7

49.0(5.0kgf.m)

53.9(5.5kgf.m)

Material and dimension of connection pipe

Confirm drainage

Perform test run to insure the condition of drainage, the connection part
of the connection should not leak water. The confirmation must be
performed even if install in winter.