Warning – Emerson CF2500HTW01 User Manual
Page 9
14. Use three 10-24 x 3/8" pan head screws and flat
washers (supplied) to secure flange to blade
(blades ordered separately) (Figure 22). Repeat
for the remaining four blades.
15. Using the 5/32” hex wrench (supplied), loosen the
setscrew in the collar and unscrew (counterclock-
wise) the switch housing assembly from the motor
shaft (Figure 23). Do NOT remove the flat washer
from the motor shaft.
16. Use the 10 round recessed holes in the motor hub
marked with "5" and install the five blade assemblies
in accordance with Step 17.
17. Loosely attach one blade assembly to the motor
hub using two 10-32 x 5/8" oval head screws
(supplied) (Figure 23). Make sure the screws are
NOT tightened at this time. Repeat this procedure
for the four remaining blade assemblies.
9
10. Screw two 1” threaded studs (provided) into the
motor (Figure 20). Leave approximately 7/8” of the
stud extending above the motor. Slide the motor
cover over the downrod and rotate the cover until
the threaded studs protrude; install two knurled
knobs (supplied) to secure the cover.
NOTE: Make sure the red and brown leads are
separately capped with wire connectors. Make
sure red, brown, and yellow wire connectors are
completely inside motor coupling cover and not
pinched between the motor coupling cover and
motor.
11. Position the ceiling cover over the downrod. Be
sure the cover is oriented correctly, with the large
opening at the top (Figure 21).
12. Reinstall the hanger ball on the downrod as
follows. Route the motor leads through the hanger
ball and slide the hanger ball over the downrod
(Figure 21). Install the pin through the holes at the
top of the downrod and slide the hanger ball up
the downrod, aligning the ball so the pin is
captured in the groove in the top of the hanger
ball. Pull the hanger ball up tight against the pin
and securely tighten the setscrew in the hanger
ball. A loose setscrew could create fan wobble.
13. The blue, black, yellow and white leads exiting the
downrod are 80-inches long. Before installing fan,
measure up approximately 6 to 9-inches above the
ball/downrod assembly. Cut off excess leads and
strip back insulation 1/2-inch from end of leads.
NOTE: If you are installing your fan with a SR330
Remote Control or SW350 Wall Control, Do Not
Cut Terminal Off of the Yellow Lead.
(See Section A.)
MOTOR
DOWNROD
SETSCREW
Figure 19
KNURLED KNOB
1" THREADED
STUD
MOTOR
COUPLING
COVER
7/8"
MOTOR
WIRE
CONNECTORS
WIRE CONNECTOR
RED LEAD
BROWN LEAD
YELLOW LEAD
Figure 20
SETSCREW
DOWNROD
PIN
HANGER BALL
CEILING COVER
Figure 21
FLAT WASHER (3)
BLADE
10-24 x 3/8" PAN HEAD
SCREW (3)
BLADE FLANGE
Figure 22
10-32 X 5/8"
OVAL HEAD SCREW
(3 PER BLADE
ASSEMBLY)
MOTOR HUB
BLADE FLANGE
FLAT WASHER
(DO NOT REMOVE)
Figure 23
It is critical that the pin in the hanger ball is properly
installed and the setscrew securely tightened.
Failure to verify that the pin and setscrew are
properly installed could result in the fan falling.
WARNING
!