3.7. PHASE 6 - ASSEMBLY OF FRAME SUPPORT (element 5)
Place the frame support (element 5) with the opening aligned with Forma Puro115, 10 mm from the hood
support,10 mm from each side and 20 mm from the edge-cover profile (see figure).
Fasten the frame support to the wall using the plasterboard screws provided (12) and using the holes that are
already present. If the wall has been constructed as per paragraph
3.6. Phase 5, the screws will be located at the
steel uprights.