Ion Science Hydrosteel 7000TL User Manual
Page 7
Hydrosteel 7000TL MANUAL
Ion Science Ltd
Page 7 of 18
Unrivalled Detection. www.ionscience.com
Installation procedure
1) I identify installation location and mounting method
2) Pre-Charge the battery in safe area
3) Move all equipment to installation site
4) Mount HY7K-TL system using beam claps to suitable hand rail or other structure
5) HY7K installation. Please refer to HY7K manual
a. Mount probe
b. Mount probe bracket
c. Connect sample conduit to probe
d. Terminate sample conduit (Connect Cut to length as appropriate)
e. Connect sample conduit to HY7K instrument
f. Mount Hy7K instrument within impact protection, (if not already mounted).
g. Clad probe for weather protection
6) Battery mounting
a. Fit battery mounting bracket if it is not already secured onto the mounting struts.
b. Fit battery box into bracket as described by sliding it in for the top with the switch and
connector upper most.
7) Connect battery to HY7K using jumper cable supplied.
8) Switch over ride power on. Check HY7K switches on after ~15 seconds as indicated by the
illumination of the Red ELD on the outside of the HY7K.
9) Check operation of HY7K (HY7K Manual)
a. Let instrument run for at least 2 measurement cycles.
b. Perform data download and confirm operation. Use lap top computer loaded with ISL
software.
10) Program timer. (Timer instructions sheet as referenced)
a. Test timer. Program time with an imminent switch on and watch to ensure correct switch
on.
b. The program timer with full program.
Leave instrument to run over night. Data download should be performed in next day or so to confirm timing
is acceptable.