D.

Wiring Requirements

1.

120 VAC Supply Line
Route a copper 12 AWG, with ground, 120 VAC
supply line from the time delay fuse or circuit breaker
box to the roof opening.

a.

This supply line must be located in the front

portion of the 14-1/4" x 14-1/4" (±1/8") opening.

b.

The power MUST be on a separate 20 Amp time

delay fuse or HACR circuit breaker.

c.

Make sure that at least 15" of supply wire

extends into the roof opening. This ensures and
easy connection at the junction box.

d.

Wiring must comply with all National, State and

Local Wiring Codes.

e.

Use a steel sleeve and a grommet or equivalent

methods to protect the wire where it passes into
the opening.

E. Placing Air Conditioner On The Roof

This unit weighs approximately 100 pounds.
To prevent back injury, use a mechanical hoist
to place Air Conditioner on roof.

FIG. 7

Do not slide the unit. This may damage the
roof gasket attached to the bottom and may
create a leaky installation.

CAUTION

1. Remove the air conditioner from the carton and dis-

card carton. See FIG. 7.

2. Place the air conditioner on the roof.
3. Lift and place the unit over the prepared opening using

the gasket on the unit as a guide. See FIG. 8.

4. Place the 3105457 Mechanical Air Distribution Box

Kit inside the RV. This box contains mounting hard-
ware for the air conditioner and will be used inside the
RV. See FIG. 7.

This completes the outside work. Minor adjustments can

be done from the inside of the RV if required.

F. Installing The Air Conditioner

1.

Remove air box and mounting hardware from carton.

The upper duct is shipped inside the lower duct
which is part of the ceiling template.

2.

Check for correct alignment and adjust the unit as
necessary (Roof Gasket centers over 14-1/4" ±1/8"
opening).

FIG. 8

FRONT

FIG. 10

Step a
Remove At
Perforation

Step b
Remove At
Perforation

Step c
Use As
Packaged

Upper Discharge
Air Duct

Lower Discharge
Air Duct

Rear Of Air
Conditioner

Upper Discharge
Air Duct

Edge Without
Flange To
Rear Of Unit

FIG. 9

3.

Remove upper duct from ceiling template and locate

it over blower discharge. See FIG.9.

Note: Edge without flange installs toward REAR of opening.

4.

Use two (2) sharp pointed #10 sheet metal screws

to hold duct to base pan. Screw holes are provided
in bottom of base pan for these screws.

5.

Reach up into return air opening of the air conditioner

and pull the unit electrical cord down for later
connection.

6.

Measure the ceiling to roof thickness:
a. If distance is 1"-2", remove perforated tabs from

both upper and lower ducts. See FIG. 10.

b. If distance is 2"-3", remove perforated tabs from

bottom duct only. See FIG. 10.

c. If distance is 3"-4", install ducts as received.

See FIG. 10.

d. If distance is 4"-6", use optional 318556.000

Duct Adaptor and 3100895.006 Bolt Kit. See
FIG. 10.

600312 & 600315 Series Installation Instructions