Title: Southern States –
LLS-I-2000, LLS-II-2000 and LLS-II-3000
Load and Line Switchers
Product Specification Guide
Page 4 of 5
Publication No.: PSG-805-080109
5.02 Leak
Test
An SF
6
leak test shall be performed to confirm the leak rate is less than 0.5% per
year.
5.03 Resistance
Test
5.03.01 Current Path Resistance Test
A micro-ohm resistance check shall be performed on each interrupter
using a 100 A DC source and the values shall be recorded.
5.04 Dielectric
Test
5.04.01 Interrupter Dielectric Test
Each complete interrupter assembly shall pass a 60 Hz power frequency
withstand test for one minute.
6.0 SPARE PARTS
No spare parts shall be required at the time of load and line switcher purchase. Stock
shall be maintained at the manufacturer and available for rush shipment in the event of
an emergency need.
7.0 DOCUMENTATION REQUIREMENTS
7.01 Approval
Drawings
The manufacturer shall furnish approval drawings in AutoCAD .DWG format via
e-mail. The purchase order will designate the name and e-mail address of the
individual where the drawings should be forwarded. If there are no comments to
the approval drawings purchaser will respond via e-mail that drawings are
approved as submitted with no changes. If comments are required then one
copy of the drawings will be returned to the manufacturer within 10 days from the
date of transmittal marked “approved with comments as noted”.
7.02 Final
Drawings
The manufacturer shall furnish final drawings in AutoCAD .DWG format via e-
mail. Unless otherwise specified in the purchase order, the final drawings will be
forwarded to the same individual that the approval drawings were sent to.
7.03 Instruction
Books
The manufacturer shall furnish an electronic copy of each applicable instruction
book in Adobe Acrobat .PDF format via e-mail. Unless otherwise specified in the
purchase order, the instruction book(s) will be forwarded to the same individual
that the approval drawings were sent to.