Commissioning

Commissioning should only be
performed by specially trained
personnel and documented
after the certificate has been
issued.

Observe the manuals for the
indoor unit and outdoor unit
when commissioning the
entire system.

NOTE

Functional test for heating
mode.

1. Switch the supply voltage on.

2. Use the remote control to

switch on the unit and select
the heating mode, maximum
fan speed and highest target
temperature.

Final tasks

Re-fit all the dismantled parts.

Familiarize the operator with
the system.

4. Check the control system

for the unit using the
functions described in the
chapter "Operation". Timer,
temperature setting, fan speeds
and changing to ventilation or
dehumidification mode.

5. Check the correct function

of the condensation line by
pouring distilled water into the
condensation tray.
A bottle with a spout is
recommended for pouring the
water into the condensation
tray.

Functional test for cooling
mode.

1. Switch the supply voltage on.

2. Use the remote control to

turn on the unit and select
the cooling mode, maximum
fan speed and lowest target
temperature.

3. Measure and record all

the required values in the
commissioning report and
check the safety functions.

3. Measure and record all

the required values in the
commissioning report and
check the safety functions.

4. Check the control system for

the unit using the functions
described in the chapter
"Operation".
Timer, temperature setting, fan
speeds.

Check that the stop valves
and valve caps are tight after
carrying out any work on the
refrigerant circuit. If necessary,
use appropriate sealant
products.

NOTE

23

Unit dimensions

We reserve the right to modify the dimensions and constructional design as part of the ongoing technical development process.

All values in mm

MXW 200 - 260

250

750

205

280

815

215

MXW 350

MXW 520

292

920

224

This manual is related to the following products: