INSTALLATION INSTRUCTIONS FOR TD92 PTO DRIVELINE UPDATE:
1. The following tools are required for this installation: small
hand grinder, welder, ¾” wrenches, 5/32” allen wrench
and tape measure.
2. Use the grinder to remove the paint from the hitch (4) as
shown in sketch.
3. Remove the PTO spacer (9) from the end of the shaft (3).
4. Take the intermediate shaft and slide the end with the bell
shielding onto the main gearbox (1).
5. Take the PTO mounting bracket assembly (8) and set it on
top of the hitch, sliding the PTO end through the flange
bearing (7). Note the position of the flange bearing. Must
be on the back side.
6. Make sure the PTO shaft is tight up against the flange
bearing and tighten the two set screws (6) in the bearing.
7. Position the complete unit on the hitch so the PTO
mounting bracket is centered on the hitch, side to side, and
then slide forward or backwards until the main gearbox
(1) shaft is flush or extended 1/16” inside the PTO yoke
(2).
8. Tack weld the mounting plates to the hitch rails, and
check all dimensions.
9. Unbolt the PTO mounting bracket (8) from the mounting
plates (5) and remove both the bracket and the PTO shaft.
10. Finish welding the mounting plates to the hitch.
11. Clean and paint the mounting plates. Use International
Harvester red spray paint (IH2150 RED) for best match.
12. Remount the PTO and PTO mounting bracket to the hitch.
Follow the instructions to ensure proper set up and shaft
alignment to suit your tractor.
13. Be sure to install the PTO spacer back (9) on the PTO
shaft end (3) before installing the input PTO.
14. Bolt the hose support guard (10) to the mounting bracket.