Float adjustment, Maintenance and repair – MEGA Corp. MPT User Manual
Page 17
MPT12 Manual
26 Mar 2014
SECTION 5
Maintenance and Repair
5-2
7. Mix Epoxy or Urethane coating according the
manufacturer’s instructions.
8. Apply coating with roller or natural haired brush.
Ensure coating in applied at the manufacturer’s
recommended thickness. See MSDS sheet for
details.
9. Allow sufficient time for the coating to cure
before filling tank with water.
Leaks
1. Remove paint and corrosion from suspected area.
2. Weld over leak.
3. Prime and paint over weld.
Structure
Contact MEGA Product Support for assistance on
major structural repair at US toll free: 1-800-345-8889
Direct: 1-505-345-2661 or visit our website at
for more detailed contact
information.
FLOAT ADJUSTMENT
SINGLE FILL PIPE
1. Open flow control valve all the way. then close.
2. Open flow control valve 3 to 3-1/2 turns.
3. Start fill.
4. Water should be coming out of float valve (if not
open flow control valve ¼ turn).
5. Pull up on float.
6. If water will not shut off, close flow control
valve ¼ of a turn.
7. Pull up on float (adjust control valve until water
shuts off ).
DOUBLE FILL PIPE
1. Make sure both shut off valves are open before
adjusting.
2. Open flow control valves on both fill pipes all the
way. then close.
3. Open flow control valves on both fill
pipes 3 to 3-1/2 turns.
4. Start fill.
5. Water should be coming out of float valve (if not
open flow control valve ¼ turn).
6. Pull up on float.