Flowserve OR 52-7 User Manual
Page 18

8
Commissioning Procedure
– continued –
First commissioning
. Apply supply voltage to the measuring transducer.
The green LED ON will be illuminated and alarm 2 is
signaled.
2. When the equipment is switched on, the system window
appears for approx. 3 seconds, indicating the following:
Name of the equipment,
Certificate,
Serial number,
Number of the software version.
3. After approx 3 seconds the measurement window
appears, indicating the following:
Oil content (in large characters),
State: Warm up
Current time / date in UTC
4. After approx. 30 seconds the actual value in ppm is
indicated in the measurement window. If this value is
below 5 ppm the message Alarm 2 is cancelled and the
equipment state “Ready” is indicated. If, however, the
value continues to exceed 5 ppm, the message Alarm 2
remains active and the equipment state “ppm>Limit” is
indicated.
5. Press now key
+. The purging valve opens and Alarm 2 is
indicated. The equipment state “Clear Water ON” appears.
Rinse the measuring transducer ORG 2 for at least
5 minutes with oil-free water and operate the cleaning
device
4 2 – 3 times, Fig. 5. During the rinsing process
with oil-free water the measuring window should show
0 ppm. If this is not the case switch to programming
mode, Parameter Value Offset, and reduce the zero point
by a max. of 5 ppm.
6. To close the purging valve press key
–. The equipment
state “Ready” or “ppm>Limit” or any other alarm message
is indicated.
Note that in the measurement window the keys and and “OK” do not have a function. If you
want to enter the programming mode press key
P.
Device
Certif.
Ser.Nr.
Vers.
: ORT7
: IMO
: MEPC.107(49)
: 392358
: 311137.10
Flowserve Gestra
OIL CONTENT :
ppm
State: WarmUp
8
UTC 10:46
2006-12-06
OIL CONTENT :
ppm
State: ready
8
UTC 10:46
2006-12-06
OIL CONTENT :
ppm
State: ClearWater ON
0
UTC 10:46
2006-12-06