AKH2 -
atomac ball valve - full port
Ahaus GmbH
von-Braun-Straße 19a
D-48683 Ahaus
Postfach 1162 D-48661 Ahaus
Telefon: +49(0) 2561-686-100
Fax: +49(0) 2561-686-200
Register:
2
Page:
9
Date:
12.1995
Revision:
02.2009
Technical Manual
Assembly Instructions AKH2
The general installation and maintenance instructions must be observed.
1. Screw stud bolts
(120) into body (010).
2. Insert stem
(040) from inside of body in such a way that the flat side is paral-
lel to body longitudinal axis.
3. Insert chevron packing
(100).
4. Install gland insert
(065), gland follower (060), safety washers (150), hexa-
gon nuts
(110) and grounding strap (170) also on valves with actuator.
5. Install hand lever
(070) on to stem (040) and tighten it using lock washer
(130) and hexagon bolt (140).
6. Insert first ball seat ring
(030) into body (010).
7. Insert ball
(050) to valve stem by pushing the ball in a downward motion
through valve body.
8. Turn hand lever 90° of longitudinal axis of body.
9. Install second ball seat ring
(030) on to ball (050).
10. Install side piece
(020) on to body
(010), making sure that recess for
stem is on the correct side.
11. Install body bolts
(080) and hexagon
nuts
(090) and tighten by crisscross
method to recommended torques.
12. Assemble stop
(210) with hexagon
bolt
(220).