3 - Cascade – Heating only

Managing Boiler
Boiler is set as Managing (address = 1), controller of this

boiler will drive cascade.
CH mode of managing boiler applies to all other boilers. It

is only required to set CH mode on managing boiler.

• Outdoor temperature sensor connected to MANAGING

boiler is outdoor sensor for cascade operation

• System sensor connected to MANAGING boiler is control

sensor for cascade supply temperature.

• Thermostat connected to MANAGING boiler is CH heat

demand input for cascade system.

Managing boiler calculates required boiler setpoint to

achieve requested cascade setpoint.
Managing boiler provides calculated setpoint to all

dependent boilers.
Power of dependent boilers is Proportional Intergral

Derivative (PID) controlled on basis of calculated setpoint

and dependent boiler supply temperature.

CH Mode
Set CH mode at managing boiler.

CH Setpoint For Boilers
When system temperature is not high enough, setpoint for

all boilers will be adjusted. Boiler setpoint will be increased

when system temperature is below cascade setpoint and

decreased when it is above cascade setpoint temperature.
This is determined as following:

• PID-control loop over system temperature calculates

adjustment of boiler setpoint.

• When system temperature is above cascade setpoint,

calculated boiler setpoint will be decreased by a

maximum of -10ºC (-18ºF). In case system temperature

is below cascade setpoint, calculated boiler setpoint

to all boilers will be increased by a maximum of 20ºC

(36ºF).

• Calculated boiler system setpoint will be limited at 85ºC

(185ºF).

• PID calculation does not start immediately, delay period

allows system to stabilize. Delay period is calculated

by multiplying Start Time delay setting with Start

Modulation Delay Factor (settable).

• Delay period is limited to 60 minutes. Setting Start

Modulation Delay to 0 disables this function.

Dependent Boiler

• Dependent boiler (address = 2-16) always receives its

setpoint from managing boiler.

• Firing rate of ALL boilers is PID controlled by individual

boiler. Individual boiler calculated setpoint is received

from managing boiler to control boiler supply

temperature.

• Managing boiler will operate in cascade system similar

to a dependent boiler, except it will also control external

pumps and analyze data collected by system and

outdoor sensors.

• Maximum dependent boiler temperature is fi xed at 91ºC

(196°F).

4 - Cascade – Domestic Hot Water

Connections:
Wire external tank thermostat to DHW T-T input on

managing boiler terminal block.
Pump for DHW operation is connected to managing boiler

DHW pump high voltage terminals.

Settings:
Set DHW setting, in Installer menu of managing boiler

control, as follows:

• Set DHW mode at 2.
• Set DHW Boiler Assign to ALL in Installer CASCADE

menu of managing boiler.

Control functions as described in boiler's Installation,

Operation and Maintenance Manual, when demand for DHW

is detected.

Dependent Boiler
Dependent boilers (address =2-16) receive DHW setpoint

from managing boiler.