Wall Mounting Instructions for Screens with 24” Marker Tray
NOTE: The screen is shipped with two wall brackets. Screens in 
widths of 84 ¾” and below receive (2) 28” wall brackets. Screens 
above 84 ¾” in width receive (2) 44” wall brackets. Use 
appropriate mounting hardware for the wall type and to 
accommodate for the screen’s hanging weight (Figure 2).
1. Secure the two wall brackets to wall studs at the desired height.
The outside edge of each wall bracket must be no greater than 
5” away from the left and right edges of the frame. You will need 
at least 1” clearance above the drilled holes to hang the screen 
(Figure 2) .
2. To install the (2) L-brackets, you must measure the overall height
of the screen frame and subtract 1⅛”. Using that dimension, 
measure down from the top edge of the wall brackets and mark 
the wall for two screw holes. The outside edge of each L-bracket 
must be no greater than 5” away from the left and right edges of 
the screen frame (Figure 2).
3. Secure the two L-brackets to the wall at the marked locations. The
longest side of the two L-brackets should be pointing upwards 
when secured in order to hide the L-brackets behind the screen 
frame once the screen is installed.
Wall Brackets
L-Bracket
No More 
than 5”
No More 
than 5”
No More 
than 5”
Figure 2
Screws (Not Supplied)