Commissioning Check List
General
!
All equipment ordered by the customer is installed.
!
The unit is level and secure.
!
The mains and control wiring are complete and the circuit breaker and GPO are turned ON.
!
All Controller functions for the appliance operate.
!
All electrical or water connections are to manufacturers specifications and the relevant electrical or
plumbing standards and codes.
Unit - Ducted Evaporative Air Conditioner
!
The water supply line has been flushed to clear swarf and debris and is free of leaks.
!
The tank is free of foreign matter and debris and the water isolating tap is turned ON.
!
Water drainpipe work is completed and sealed.
!
The water basin fills with water and the float valve closes correctly when the water level is 35 -
40mm below the overflow level.
!
The water pump operates correctly when turned ON at the controller.
!
The Dialflo water bleed rate is adjusted to suit local water conditions.
!
The Superclean Dump Valve (option). The tank drains correctly when unit turns off.
!
The fan deck is correctly located and the fan blade spins freely.
!
The fan operates through the entire speed range.
!
The minimum fan speed is correctly set.
!
Water distribution is even with the filter pads fitted and the air conditioner operating pump and fan.
!
Areas of high water pressure (Exceeding 500Kpa) a water pressure limiting valve must be fitted in
accordance with AS3500. Consequential damage from high water pressure is not covered by
warranty.
Ductwork
!
All ductwork is completed to plan, correctly supported and airtight, with no bend less than 1.5 x the