22
Figure 27: Cable Configurations: C03, C13, C11, C12 and C18
6. Route C11 to the rear of the sprayer,
in the vicinity of the valve block.
7. Connect the 6-pin shroud on C12 to
the mating connector on C11.
8. Route the free end of C12 to the
existing left and right boom control
valve block.
9. Unplug the connectors on the existing
valves. There are 4 connectors to
unplug (as labeled on the valve bank):
LEFT UP, LEFT DOWN, RIGHT UP and
RIGHT DOWN. Plug in the 2-pin
Receptacle of C12 to the matching
existing valve connections. For each
connector, the function (e.g. “LEFT UP”,
etc.) is labeled on the branch wire.
10. Connect the 2-pin tees (which are
labeled as “MAIN UP” and “MAIN
DOWN” on the branch wires) of C12
to the matching tees of the main
extension interface cable (C18).
11. Route the free end of C18 to the
existing main control valve block.
12. Insert the 2-pin tees of C18 between
the matching main control valve
connections.
13. Connect the 6-pin Tower on the valve
cable (C03) to the mating connector on
C11.
14. Connect the 3-pin Shroud on the bypass
cable (C13) to the mating connector on
C11.
15. Install the Deutsch connectors from
C03 onto each NORAC valve as shown
in Figure 28.
16. The connectors on the valve cable
(C03) are marked RIGHT UP, LEFT
UP, RIGHT DOWN and LEFT
DOWN. Cables labeled with UP go
on the same side as the hydraulic hoses
Figure 28: Valve Cable Connections