beautypg.com

2 valve mounting – NORAC UC4+BC+CS2 User Manual

Page 21

background image

18

4.6.2 Valve Mounting
1. Mount the NORAC valve (V01) on the

sprayer using the valve mounting
bracket (B10).

2. As shown in Figure 22, screw short

side of the threaded rods into the
bottom of the valve block at least 3/8".
The valve mounting holes are drilled and

tapped 3/8 NC-1" deep.

3. Tighten the Hex nuts to hold the rods.

4. Put the mounting bracket on the other

side of the tube and tighten with the
spring washers and the Hex nuts.

5. Cut excess off of the rods, if necessary.

6. Figure 23 shows the NORAC valve

mounted on the sprayer.

If using bolts, the bolts should

thread into the valve block at

least 3/8". The valve mounting
holes are drilled and tapped 3/8
NC-1" deep. The rule of thumb
for bolt length is 1-1/2" longer
than the tube size.

You must ensure no hydraulic

components will interfere with
any sprayer parts or be pulled
tight at any time.








Figure 22: Valve Mounting Location

Figure 23: Valve Mounting Example

You must also ensure there are

no other orifices present in the
circuit between the NORAC
valve block and the boom
cylinders.