5 Electrical Installation

Figure 9: Cable Connections

Only parts shown in black are included in this kit.

1. Connect the 6-pin shroud (S6) on C17 to T6 on C11 (previously installed).

2. Connect the 3-pin tower (T3) on C17 to S3 on C11.

Two connectors on C17 will remain disconnected. These are used when

installing other UC4.5 options.

3. Install the two 2-pin connectors on the end of cable C17 to the expansion block.

The connector marked “Main Up” goes on the port side of the block. The

port side of the block is the side with the hose connections.

4. Connect the main lift sensor to the 8-way coupler using cable C07 and a 2-way coupler

(E12). Cable C07 and item E12 may not be needed if the 8-way coupler is mounted close
enough to the main lift sensor.