background image

Operating instructions

W4D710-GF01-01

Translation of the original operating instructions

4.5 Open additional screwed cable glands

You have the ability to break a second cable gland opening through on
the terminal box.

WARNING
In event of a fault, the screwed cable gland is under
electrical voltage
Electric shock
→ Do not use metal cable glands for plastic terminal

boxes.

; Screw the cable gland into the pre-cut thread using a screwdriver.

When doing so, note the tightening torques, see chapter 3.1 Product
drawing.

; Remove the plastic tab that falls off when the wire is pressed through

into the terminal box.

Fig. 4: Screwed cable gland opening

4.6 Checking the connections

; Make sure that the power is off (all phases).
; Secure it from being switched on again.
; Check the correct fit of the connection lines.
; Screw the terminal box cover closed again. Terminal box tightening

torque, see chapter 3.1 Product drawing.

; Make sure that the terminal box is correctly closed and sealed and

that all screws and screwed cable glands are properly tightened.

4.7 Switch on device

The device may only be switched on if it has been installed properly and
in accordance with its intended use, including the required safety
mechanisms and professional electrical connection. This also applies for
devices which have already been equipped with plugs and terminals or
similar connectors by the customer.

WARNING
Hot motor housing
Fire hazard
→ Ensure that no combustible or flammable materials are

located close to the fan.

; Inspect the device for visible external damage and the proper function

of the protective features before switching it on.

; Check the air flow paths of the fan for foreign objects and remove any

that are found.

; Apply the nominal voltage to the voltage supply.

4.8 Switching off the device

; Disconnect the device from the supply voltage at the main switch for

the supply line.

; When disconnecting, be sure to disconnect the earth wire connection

last.

Item no. 10935-5-9970 · Revision 82513 · Release 2014-06-10 · Page 9 / 10

ebm-papst Mulfingen GmbH & Co. KG · Bachmühle 2 · D-74673 Mulfingen · Phone +49 (0) 7938 81-0 · Fax +49 (0) 7938 81-110 · [email protected] · www.ebmpapst.com