TROUBLESHOOTING GE ECM2.3

MOTORS

CONT’D.

Replacing ECM Control Module

To replace the control module for the GE variable-speed indoor blower
motor you need to take the following steps:

1. You MUST have the correct replacement module. The controls are

factory programmed for specific operating modes. Even though they look
alike, different modules may have completely different functionality.

USING THE WRONG CONTROL MODULE VOIDS ALL PRODUCT
WARRANTIES AND MAY PRODUCE UNEXPECTED RESULTS.

2. Begin by removing AC power from the unit being serviced. DO NOT

WORK ON THE MOTOR WITH AC POWER APPLIED. To avoid
electric shock from the motor’s capacitors, disconnect power and wait at
least 5 minutes before opening motor.

3. It is not necessary to remove the motor from the blower assembly, nor

the blower assembly from the unit. Unplug the two cable connectors to the
motor control assembly. There are latches on each connector. DO NOT
PULL ON THE WIRES. The plugs remove easily when properly
released.

4. Locate the screws that retain to the motor control bracket to the

sheet metal of the unit and remove them. Remove two (2) nuts that
retain the control to the bracket and then remove two (2) nuts that
retain sheet metal motor control end plate. Refer to Figure 10.

5. Disconnect the three (3) wires interior of the motor control by

using your thumb and forefinger squeezing the latch tab and the
opposite side of the connector plug, gently pulling the connector. DO
NOT PULL ON THE WIRES, GRIP THE PLUG ONLY. Refer to
Figure 10.

6. The control module is now completely detached from the motor.

Verify with a standard ohmmeter that the resistance from each motor
lead (in the motor plug just removed) to the motor shell is >100K
ohms. Refer to Figure 11. (Measure to unpainted motor end plate.) If
any motor lead fails this test, do not proceed to install the control
module. THE MOTOR IS DEFECTIVE AND MUST BE
REPLACED. Installing the new control module will cause it to fail
also.

7. Verify that the replacement control is correct for your

application. Refer to the manufacturer's authorized replacement list.
USING THE WRONG CONTROL WILL RESULT IN
IMPROPER OR NO BLOWER OPERATION. Orient the control
module so that the 3-wire motor plug can be inserted into the socket in
the control. Carefully insert the plug and press it into the socket until
it latches. A SLIGHT CLICK WILL BE HEARD WHEN
PROPERLY INSERTED.

8. Reverse the steps #5, 4, 3 to reconnect the motor control to the

motor wires, securing the motor control cover plate, mounting the
control to the bracket, and mounting the motor control bracket back
into the unit. MAKE SURE THE ORIENTATION YOU SELECT
FOR REPLACING THE CONTROL ASSURES THE
CONTROL'S CABLE CONNECTORS WILL BE LOCATED
DOWNWARD IN THE APPLICATION SO THAT WATER
CANNOT RUN DOWN THE CABLES AND INTO THE
CONTROL. DO NOT OVERTIGHTEN THE BOLTS.

9. Plug the 16-pin control plug into the motor. The plug is keyed.

Make sure the connector is properly seated and latched.

10. Plug the 5-pin power connector into the motor. Even though

the plug is keyed, OBSERVE THE PROPER ORIENTATION. DO
NOT FORCE THE CONNECTOR. It plugs in very easily when
properly oriented. REVERSING THIS PLUG WILL CAUSE
IMMEDIATE FAILURE OF THE CONTROL MODULE.

11. Final installation check. Make sure the motor is installed as follows:

a. Motor connectors should be oriented between the 4 o’clock

and 8 o’clock positions when the control is positioned in its
final location and orientation.

b.Add a drip loop to the cables so that water cannot enter the

motor by draining down the cables. Refer to Figure 12.

The installation is now complete. Reapply the AC power to the
HVAC equipment and verify that the new motor control module is
working properly. Follow the manufacturer’s procedures for
disposition of the old control module.

Motor

Motor OK when

R > 100k ohm

ECM 2.0

Only remove

Hex Head Bolts

Connector Orientation

Between 4 and 8 o'clock

Drip Loop

Back of

Control

Figure 5

Winding Test

Figure 4

Note:
Use the shorter
bolts and
alignment pin

supplied when
replacing an

ECM 2.0
control.

Figure 3

ECM

2.3/2.5

Power Connector
(5-pin)

Control Connector
(16-pin)

Hex-head Screws

Motor Connector
(3-pin)

Motor Connector
(3-pin)

Control Disassembly

Drip Loop

Push until

Latch Seats
Over Ramp

From Motor

Circuit

Board

Figure 11

Figure 10

Figure 12