beautypg.com

Installation, Instructions – Autoquip FREIGHTLIFT FLMC User Manual

Page 34

background image

34





B. CARRIAGE ASSEMBLY (Reference Figures 16 through 18)
Items needed:
Qty

Description

1

Carriage Weldment

1 - 2

Handrails or Expanded Metal Side Guards

1

Stanchion (for 90 degree load patterns)

1 - 2

Snap Chains – lengths vary with platform width


1. Attach handrails or side guard panels by positioning as shown in Fig. 17 and/or the

General Arrangement drawing, and welding into place with a minimum 1/4" fillet, 2” on
10”. Grind welds and touch up the paint where necessary.

2. Attach snap chain(s) across open operating ends by using the repair link to

permanently attach one end of the snap chain assembly to the open link welded to
the handrail.

3. Bolt the carriage uprights and overhead channel to the carriage as shown using the

hardware provided.


4. Set the carriage into the lower level position as shown on the General Arrangement

(GA) Drawing. The center of the carriage must be aligned with the “B” mark (refer to
Figure 16).

5. For Pit Mounted Lifts - the pit has been poured 1/2" – 3/4" deeper than the total

thickness of the carriage platform for shim and grout as required.

6. For Through-Floor or Shaft Installations – when clearances are tight, you may choose

to position the carriage after the beams have been assembled and raised into place.
For these installations, refer to Figure 18 to see how to properly lay out and locate
the beams prior to setting the carriage.

INSTALLATION

INSTRUCTIONS