Warning – Autoquip Q-LIFT User Manual
Page 16
16
5. Temporarily connect electrical service and hydraulic
hoses.
6. Fill hydraulic reservoir with proper type and volume of
fluid.
7. Press “UP button and raise lift one foot.
8. Press “DOWN” button to fully lower lift. Continue to
hold down button for 60 seconds. Repeat procedure
five to seven times to bleed air out of hydraulic system.
9. Raise and lower lift as needed to make positioning
adjustments.
10. Adjust platform to a clearance of 1” minimum around
perimeter between platform and pit angle.
NEVER go under a raised lift platform until load is removed and
lift is securely blocked in raised position with maintenance
devices.
See "Maintenance Device" section of this manual.
Lock-out/tag-out power source.
11. Base frame of lift has pre-drilled holes for anchoring floor. Anchor lift to floor. Lifts with oversize
platforms have minimum pull out requirements of 2,000 lbs. for each anchor. See “Shimming And
Anchoring Lift To Concrete”.
12. Make permanent electrical and hydraulic connections and operate lift through a few cycles.
13. Clean up debris and spilled oil from area. Dispose of oil in an environmentally safe manner.
14. Touch-up paint is available from Autoquip for repair of damaged paint surfaces.
15. Train personnel on lift operation, all safety features and procedures.
^ WARNING