6 maintenance forms, 7 co2/ln2 back-up system service checklist, Maintenance forms – Eppendorf LN2 Backup System User Manual
Page 27: Back-up system service checklist, 6 maintenance forms 8.7 co

Maintenance
New Brunswick LN2 Back-up System
English (EN)
27
8.6
Maintenance forms
8.7
CO
2
/LN
2
back-up system service checklist
Period
Place the task
Task
Personnel
Weekly
Near device
Clean with damp rag if
necessary.
User
Weekly
Near LN
2
supply
Weigh LN
2
supplies to
see if they are full.
User
Monthly
Near device
Check for cuts or
abrasions on all electrical
wires.
User
Inspect all hoses for cuts,
chaffing, and squashing.
Inspect hose connection
to bottle and seal
connection on the bottle.
There should be no
damage or corrosion.
Inspect manifold plugs
and seals. There should
be no mechanical
damage or corrosion.
Inspect LN
2
supply
connection and solenoid
valve connection. There
should be no damage or
corrosion.
Once every 5 years or
when battery fails
Near device
Replace battery.
Qualified service
engineer
NOTICE!
Service should check the following points.
Refer to user manual sections as indicated.
1.
Check Back-up system components for wear and any damage.
2.
Check system and gas supply installation (see
gas supply installation on p. 18).
3.
Check system connections for leaks (see
4.
Test the injector valve operation (see
Testing the solenoid valve on p. 21).
5.
Test the door switch operation (see
Testing door switch on p. 21).
6.
Test overall system operation (see