6
Fold Down Guardrails
This procedure is only for passing through door-
ways. Guardrails must be returned to proper
position before using the machine.
Fold Down Procedure (Figure 7)
Note: When performing the following procedures
retain all fasteners.
1. Ensure that the slide out deck extension is fully
retracted and deck pin is locked. Place the controller
on the platform.
2. Pull the pins on the two end gate arms. Lower the
rear gate to the floor. Replace the pins.
3. Pull the pins (2) on the left side of the front rail and
swing the front rail back against the right handrail.
Insert pins into right handrail.
4. Lift the right handrail up, then lower it to the exten-
sion deck floor.
5. Push the deck extension handle into locked position.
Lift the left handrail up, then lower it on top of the
right handrail.
6. Rotate the arms in against handrails.
7. Lift the right main handrail and lower to the floor.
8. Lift the left main handrail and lower it on top of right
hand rail.
Figure 7: Fold Down Guardrails
Deck
Extension
Handle
3
4
6
8
7
5
1
6
2
Before operating machine, guardrails must be
securely fastened in their proper position.
Erection Procedure
1. Reverse the fold down procedure.
2. Hang the controller from front guardrail.
3. Before operating the work platform, check that all
fasteners are in place.